Whether planning for a new rack system in a new location, or a new rack system in an existing location, the system cannot be installed until all applicable building codes have been satisfied. Further, a building permit must be issued for a particular system design that meets geographic location requirements while supporting the user’s load application. The local Authority Having Jurisdiction (AHJ) or building official will first need to verify that all code provisions will be satisfied before issuing a building permit and will issue a certificate of occupancy (CO) upon completion of the rack installation.

As for the basis of the permits themselves, many U.S. jurisdictions (but not all) utilize the 2015 International Building Code (IBC)—developed by the International Code Council—as their standard. The IBC references RMI’s ANSI MH16.1-2012: Specification for the Design, Testing and Utilization of Industrial Steel Storage Racks in section 2209.1 as the standard for safe design and installation of steel storage racks. Likewise, the National Fire Protection Associationreferences the same specification in the NFPA 5000 Building Construction and Safety Code. Key areas of inspection can include verification of proper anchorage of the racks to the floor, field welding, proper flue spaces are maintained between the racks and between the products being stored, and egress distances.

Many projects are delayed by not addressing fire safety requirements during the planning process. In many cases fire protection requirements will significantly impact the design of the rack system, as well as what can be stored in it. The permit and inspection verify that a facility’s sprinkler system and racking are properly designed and will work together effectively, as per the NFPA 13 design standard for sprinkler system installation and the International Code Council (ICC) International Fire Code (IFC) regulations. IFC Section 2302 covers permits for High Piled Storage, which is defined as storage of combustible material in closely packed piles, or combustible materials on pallets, in racks or on shelves where the top of storage is more than 12 feet high.

In order to ensure a smooth project and to minimize surprises, it is a good idea to contact the local building and planning department ahead of time. This allows a facility owner to gain a better understanding of the requirements, costs and the typical timeline for plan review, permit processing, inspections, and completed project approval.

RMI offers published guidelines for operations to review before undertaking a rack project. Get your copy of Considerations for the Planning and Use of Industrial Steel Storage Racks today.

 

Magazine & eNewsletter

Printed Monthly Magazine

Published monthly, Material Handling Wholesaler offers feature columns and special coverage of relevant industry issues and products.

Digital Monthly Magazine

Published on the fourth Thursday of each month, Material Handling Wholesaler offers feature columns and special coverage of relevant industry issues and products.

Material Handing Wholesaler Weekly Newsletter

Our Weekly newsletter is emailed every Tuesday and contains the latest Industry Events and People News, Source Directory, and important Industry Links.

Forklift International Weekly Hot Sheet Newsletter

Published every Monday morning with the latest material handling equipment
available for sale.

Share the Post:

Related Posts

Our Current Issue

Magazine & eNewsletter

Our magazine is published and mailed monthly, Material Handling Wholesaler offers feature columns and special coverage of important industry issues. 

Weekly Newsletter – Get the latest industry events and people news in this weekly e-newsletter as well as direct access to Wholesaler’s Source Directory and link.

Current Supplements







Steady Hands in Shifting Sands: Maintaining Your Dealership’s Edge

Listen to this article In the September issue, we typically cover the latest developments in finance, rental, and leasing, providing…

Caldwell launches custom lifting beam with LGH

Listen to this article A new lifting beam that enables forklifts to more efficiently carry longer loads is now in…

Fed holds rates steady amid diverging views; Manufacturing outlook remains strong

Listen to this article The Federal Reserve held the federal funds rate steady at a target range of 4.25% to…

Seeking Nominations: 25th Salute To Women in Material Handling Cover Story

Listen to this article Do you know an exceptional woman making an impact in the material handling industry? Material Handling…

The PTDA Manufacturer-Distributor Idea Exchange evolves as the largest direct networking event for PT/MC Channel Partners

Listen to this article In response to demands for more effective tools for accelerating supply chain relationships, the Power Transmission…